Periodic maintenance of Oil Immersed Transformers in
its foundation or our company - Up to 420 kV System
Voltage:
Oily Distribution and Power Transformers can gain a
lot with respect to their technical lifetimes
in case their monthly, biannual, annual, two-year and
five-year periodic maintenance is performed.
Accordingly, the process of protective periodic maintenance
is very important for transformers.
Repairation of Oil Immersed Distribution and Power Transformers
- Up to 36 kV:
Transformers face temporary regimon many times during
their operation. Protection systems
protect transformers against these temporary incidents,
from time against overcharge,over
voltage, from time to time against short circuits. Despite
this, transformers still break-down. Our
firm performes the required repair of defective transformers
by remaining loyal to the original
there of meticulously and reliably.
To make test of Oil Immersed Distribution and Power
Transformers :
In case our customers need it, they may request from
our firm performance of site tests of
their transformers. Our firm turns the site tests performed
into a report and submits to our
customer's attention by interpreting it if desired.
Oil
treatment of Oil Immersed Transformers in its foundation
or our company :
Oily transformers operate under different temperatures
due to change of charge during
operation. The heating transformer oil expands sometimes
a little, sometimes much. During
those times, it inhales and exhales air by means of
a Humidity Remover from the Expansion
Depot. No matter how much the oil performs this air
inhale and exhale by means of the hu-
midity remover, because of the fact that sometimes the
humidity remover is full with humidity
and sometimes rhe weather is very humid, it catches
humidity in the long run. Moreover, under
effect of it's heating also, it slowly becomes sediment.
This humidity penetrates the insulation of
the rolls also. At the protective periodic checks performed,
this situation is identified in the die-
lectric tests of the oil. If need be, some tests are
also applied to the oil and transformer for the
oil according to the size, voltage and significance
of the transformer, and the Oil Discaharge Process is
decided upon. Our firm serves on this matter including
power transformer up to a system voltage of 380 kV.
Repairation of Swichgear in its foundation or our company
:
Our firm also performs repair work of Partially or Fully
Oiled, SF6 Breakers and also Seperators
on the system beside transformers, and remedies our
customer's problems. Periodic maintenanceof
Swichgear in its foundation or our company :
In case it's requested, on site or at our premises,
the maintenance work of Oily and SF6
Breakers are performed by our firm. Moreover, some function
tests can also be applied.